Stage 2 Criteria (from the PLD) | Meets / Needs Improvement / Missing / Not Applicable | Supporting Data (if needed, include links to specific examples) |
---|---|---|
Development of a growth plan (to include both roadmap of projected feature sets as well as overall community growth/project maturity), to be done in conjunction with their project mentor(s) at the TAC. | Meets | Within Akraino, there is currently
|
Document that it is being used in POCs. | Meets | Each Blueprint (Integration) project is required to submit the followng set of Documents:
|
Demonstrate a substantial ongoing flow of commits and merged contributions. | Meets | There had been 623 committs, by 62 contributors over 36 repositories. https://lfanalytics.io/projects/lfedge%2Fedgex-foundry/dashboard |
Demonstrate that the current level of community participation is sufficient to meet the goals outlined in the growth plan. | Meets | There have been more than 17.00K builds. lfanalytics.ioinsights.lfx.linuxfoundation.org/projects/ lfedge%2Fedgexfoundry |
Demonstrate evidence of, or a plan for, interoperability, compatibility or extension to other LF Edge Projects. Examples may include demonstrating modularity (ability to swap in components between projects). | Meets | There are undertakings for high-level co-operation between Akraino ELIOT and EdgeX Foundry. Thwre are also several cases for interaction/use of LF Edge EVE and Fledge (e.g. Akraino Blueprint IoT Camera maintenance Blueprint). Akraino API TSC Sub-committee is currently workingon assessing the room for potential co-operation among Akraino Blueprint and Development Projects as part of the Inter-operability Strategy for one of the Akraino Goals for 2021. |
...